Civil Engineering Gate Yearwise
Civil Gate 2025 Set-2
Civil Gate 2024 Set-1
Civil Gate 2024 Set-2
Civil Gate 2023 Set-1
Civil Gate 2023 Set-2
Civil Gate 2022 Set-1
Civil Gate 2022 Set-2
Civil Gate 2021 Set-1
Civil Gate 2021 Set-2
Civil Gate 2020 Set-1
Civil Gate 2020 Set-2
Civil Gate 2019 Set-1
Civil Gate 2019 Set-2
Civil Gate 2018 Set-1
Civil Gate 2018 Set-2
Civil Gate 2017 Set-1
Civil Gate 2017 Set-2
Civil Gate 2016 Set-1
Civil Gate 2016 Set-2
Civil Gate 2015 Set-1
Civil Gate 2015 Set-2
Civil Gate 2014 Set-1
Civil Gate 2014 Set-2
Civil Gate 2013
Civil Engineering GATE 2020 Set-1 Questions with Answer
Ques 40 Civil
A cantilever beam PQ of uniform flexural rigidity (EI) is subjected to a concentrated moment M at R as shown in the figure.

Ques 41 Civil
A dowel bar is placed at a contraction joint. When contraction occurs, the concrete slab cracks at predetermined location(s). Identify the arrangement, which shows the correct placement of dowel bar and the place of occurrence of the contraction crack(s).
Ques 42 Civil
The relationship between traffic flow rate (q) and density (D) is shown in the figure.

Ques 43 Civil
The appropriate design length of a clearway is calculated on the basis of 'Normal Take-off' condition. Which one of the following options correctly depicts the length of the clearway? (Note: None of the options are drawn to scale)
Ques 44 Civil
The total stress paths corresponding to different loading conditions, for a soil specimen under the isotropically consolidated stress state (O), are shown below.

Ques 45 Civil
The soil profile at a site up to a depth of 10 m is shown in the figure (not drawn to the scale). The soil is preloaded with a uniform surcharge (q) of 70 kN/m2 at the ground level. The water table is at a depth of 3 m below ground level. The soil unit weight of the respective layers is shown in the figure. Consider unit weight of water as 9.81 kN/m3 and assume that the surcharge (q) is applied instantaneously.

Ques 46 Civil
Water flows at the rate of 12 m3/s in a 6 m wide rectangular channel. A hydraulic jump is formed in the channel at a point where the upstream depth is 30 cm (just before the jump). Considering acceleration due to gravity as 9.81 m/s2 and density of water as 1000 kg/m3, the energy loss in the jump is
Ques 47 Civil
A water supply scheme transports 10 MLD (Million Litres per Day) water through a 450 mm diameter pipeline for a distance of 2.5 km. A chlorine dose of 3.50 mg/litre is applied at the starting point of the pipeline to attain a certain level of disinfection at the downstream end. It is decided to increase the flow rate from 10 MLD to 13 MLD in the pipeline. Assume exponent for concentration, n = 0.86. With this increased flow, in order to attain the same level of disinfection, the chlorine dose (in mg/litre) to be applied at the starting point should be
Ques 48 Civil
An open traverse PQRST is surveyed using theodolite and the consecutive coordinates obtained are given in the table.

Ques 49 Civil
If C represents a line segment between (0, 0, 0) and (1, 1, 1) in Cartesian coordinate system, the value (expressed as integer) of the line integral ∫C [(y + z)dx + (x + z)dy + (x + y)dz] is _______.
3 to 3 is the correct answer.
Ques 50 Civil
Consider the system of equations

3 to 3 is the correct answer.
Ques 51 Civil
A rigid, uniform, weightless, horizontal bar is connected to three vertical members P, Q and R as shown in the figure (not drawn to the scale). All three members have identical axial stiffness of 10 kN/mm. The lower ends of bars P and R rest on a rigid horizontal surface. When NO load is applied, a gap of 2 mm exists between the lower end of the bar Q and the rigid horizontal surface. When a vertical load W is placed on the horizontal bar in the downward direction, the bar still remains horizontal and gets displaced by 5 mm in the vertically downward direction.

129 to 131 is the correct answer.
Ques 52 Civil
The flange and web plates of the doubly symmetric built-up section are connected by continuous 10 mm thick fillet welds as shown in the figure (not drawn to the scale). The moment of inertia of the section about its principal axis X-X is 7.73 × 106 mm4. The permissible shear stress in the fillet welds is 100 N/mm2. The design shear strength of the section is governed by the capacity of the fillet welds.

393.5 to 399.1 is the correct answer.

Total Unique Visitors