Mining Engineering Gate 2026 Questions with Answer
Ques 53 GATE 2026
In a biochemical oxygen demand (BOD) test, 15 ml of wastewater sample was diluted with distilled water to completely fill a 300 ml BOD bottle and incubated at 20 °C for 5 days. The dissolved oxygen (DO) level before and after incubation are 9.2 mg liter-1 and 4.4 mg liter-1, respectively. The BOD of the sample, in mg liter-1, is _______________. (answer in integer)
Ques 54 GATE 2026
A rake of wagons, with inter-wagon gap of 100 cm, is moving at a speed of 0.4 km per hour under a silo loading system. The dimensions of the wagon are 8 m (L) × 3 m (W) × 3 m (H). The silo stops discharging the material between the wagons. Considering the fill factor of the wagon as 0.95 and the bulk density of coal as 1.2 tonne per cubic meter, the loading rate of the silo, in tonne per hour, is _______________. (rounded off to nearest integer)
Ques 55 GATE 2026
A turbine pump is designed to generate water head of 60 m. The impeller speed of the pump is 2000 rpm and the manometric efficiency is 70%. Neglecting the impeller blade curvature, the impeller diameter of the pump, in cm, is _______________. (rounded off to two decimal places)
Ques 56 GATE 2026
The information for a dragline operation is given:
Bucket capacity: 20 m3
Bucket fill factor: 0.9
Digging and filling time: 20 s
Swinging (to and fro) time: 32 s
Dumping time: 10 s
Dragline utilization: 90%
The output of the dragline, in m3 h-1, is _________. (rounded off to one decimal place)
Ques 57 GATE 2026
In a bench blasting, as shown, 49 kg of explosive is put in each hole. The detonation time of holes, in millisecond, and the associated scale distance (SD) vs. peak particle velocity (PPV) plot for the given blast pattern is shown, with PPV = 250(SD)-1.5. Hole delay pattern: front row at 0, 25, 50, 75 ms; back row at 50, 75, 100 ms. The PPV at a distance of 100 m, in mm s-1, is ___________. (rounded off to two decimal places)

Ques 58 GATE 2026
A regular shaped cut and fill stope is shown. Pillars of size 4 m × 4 m are left at an interval of 13 m along the length of the stope (255 m long, 6.0 m wide). If the density of the mined ore is 2.5 tonne m-3, and slices are extracted to the full stope width, the total tonnage of ore recovered from the 1st slice (4.8 m thick) of the stope is ___________ ×103. (rounded off to one decimal place)

Ques 59 GATE 2026
A coal seam of 2.4 m thickness is mined with a DERD shearer at a cutting speed of 0.6 km h-1. The web depth of the cut is 0.5 m. The average cross-sectional area of coal on the AFC during transportation is 0.24 m2. For the evacuation of cut coal from the face with 10% spillage, the required minimum velocity of the AFC, in m s-1, is _______________. (rounded off to two decimal places)
Ques 60 GATE 2026
A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre) under extraction. The following information is given:
Gallery width = 4 m
Extraction height = 3 m
Extraction ratio during depillaring = 80%
Specific gravity of coal = 1.4
Incubation period = 6 months
Average working days per month = 25
In order to extract the panel within the incubation period, the minimum rate of production, in tonne per day, is _______________. (rounded off to one decimal place)
Ques 61 GATE 2026
In a uniaxial compressive strength test, a 120 Ω strain gauge of gauge factor 2.0 is pasted on the rock sample of length 110 mm as shown. At the end of the test, the change in resistance of the strain gauge is 0.5 Ω. The longitudinal deformation of the sample, in mm, is _______________. (rounded off to two decimal places)

Ques 62 GATE 2026
The best combination of explosive and initiation system for underwater blasting for rock breakage is
Ques 63 GATE 2026
A circular curve having radius of curvature 1000 m is set out by connecting two straights with a deflection angle of 60°. The apex distance, in m, is ____________. (rounded off to three decimal places)
Ques 64 GATE 2026
The observations from a correlation survey are shown. If the coordinates of points C and D are (East: 375 m, North: 1120 m) and (East: 376 m, North: 1121 m), respectively, the whole circle bearing of the line EF is
Given: CD = 3.0 m, CE = 4.2 m, ∠DEC = 1″, ∠DEF = 170°20′

Ques 65 GATE 2026
Following observations were taken using a Tacheometer with staff held vertical. The additive and multiplying constants of the instrument are 0 and 100, respectively. The reduced level (RL) of the staff station R, in m, is _______________. (rounded off to two decimal places)
Instrument station P, Staff station Q: Staff readings 1.4, 2.7, 3.9; Vertical angle 7°; RL of Q = 102 m
Instrument station P, Staff station R: Staff readings 2.1, 2.8, 3.6; Vertical angle 5°