Mining Engineering Gate 2021 Questions with Answer

Ques 53 GATE 2021


The grade-tonnage distribution for the ultimate pit of a mine is given below.

The mill cut-off grade is 0.5% Cu. The annual mining capacity (ore + waste) is 4.5 million tonne and milling capacity is 1.0 million tonne. Excavation is planned in such a way that either of the mine or the mill runs at full capacity throughout. The planned life of the mine, in years, is [round off to one decimal place]


(6.0) is the correct answer.

Ques 54 GATE 2021


A coal mine operating in three shifts produces 400 tonnes of coal per day with a face OMS of 1.0 from panel A, and 200 tonnes of coal with face OMS of 1.0 from panel B. The panel A and panel B are in parallel with resistance 0.6 Ns-2m-8 and 0.5 Ns-2m-8, respectively. If the panels are supplied with minimum permissible quantity as per CMR 2018, the requisite regulator resistance to meet the conditions in Ns-2m-8 is ________. [round off to 2 decimal places]


(1.80) is the correct answer.

Ques 55 GATE 2021


A set of three steel bars of equal cross-sectional area of 0.01 m2 are loaded, as shown in the figure. The elastic modulus of steel is 200 GPa. The overall change of length of the complete set of bars, in mm, is ________. [round off to 3 decimal places]


(0.045) is the correct answer.