Textile Engineering > GATE 2021 > Blowroom
In a modern high performance blowroom line, the correct sequence of machines is
A
Automatic bale opener → Blender → Coarse cleaner → Fine cleaner
B
Automatic bale opener → Blender → Fine cleaner → Coarse cleaner
C
Automatic bale opener → Coarse cleaner → Fine cleaner → Blender
D
Automatic bale opener → Coarse cleaner → Blender → Fine cleaner

Correct : d

Similar Questions

An opening roller in a blowroom with 100 cm length, 38 cm diameter, and 2 teeth per cm² is rotating at an angular velocity of 400 rpm to deliver fiber tufts at...
#357 MCQ
A cleaning unit in a blowroom is processing cotton at 600 kg/h. The waste generated is 2%. The lint to trash ratio is 60:40. The lint (in kg) accumulated in 8 h...
#668 NAT
Most of the seed coat particles are removed in
#770 MCQ