Textile Engineering > GATE 2013 > Combing
From the following data, calculate approximate production rate in kg/hr.
Length of lap fed per nip: 6 mm
Lap linear density: 60 ktex
Noil: 20%
Efficiency: 80%
Number of heads: 6
A
21
B
26
C
31
D
36

Correct : b

Similar Questions

For combing with forward feed, the given parameters are: Detachment setting = 15 mm, Length of feed per combing cycle = 6mm, Longest fiber length = 30 mm. Acc...
#293 MCQ
An eight head comber is running at 400 nips/min. The lap fed is 60 kilotex and noil extracted is 20%. If the feed/nip is 7 mm, then with machine utilization of...
#418 NAT
In cotton combing process, the counter-feed system gives
#448 MCQ

Related Topics