Mining Engineering > GATE 2026 > Bord and Pillar Mining - Depillaring
A bord and pillar panel has 24 developed pillars of size 40 m × 40 m (centre to centre) under extraction. The following information is given:
Gallery width = 4 m
Extraction height = 3 m
Extraction ratio during depillaring = 80%
Specific gravity of coal = 1.4
Incubation period = 6 months
Average working days per month = 25
In order to extract the panel within the incubation period, the minimum rate of production, in tonne per day, is _______________. (rounded off to one decimal place)

Correct : 860.2

Similar Questions

A trapezium has vertices marked as P, Q, R and S (in that order anticlockwise). The side PQ is parallel to side SR. Further, it is given that, PQ = 11 cm, QR...
#4 MCQ
Mosquitoes pose a threat to human health. Controlling mosquitoes using chemicals may have undesired consequences. In Florida, authorities have used geneticall...
#6 MCQ
Consider the following inequalities. (i) 2π‘₯ βˆ’ 1 > 7 (ii) 2π‘₯ βˆ’ 9 < 1 Which one of the following expressions below satisfies the above two inequalities?
#7 MCQ

Related Topics

mining engineering GATE 2026 panel extraction rate GATE mining engineering coal extraction rate mining engineering production rate panel extraction mining GATE mining panel extraction calculation mining engineering production

Unique Visitor Count

Total Unique Visitors

Loading......