Mining Engineering > GATE 2026 > Mine Methods - Cut and Fill Stoping
A regular shaped cut and fill stope is shown. Pillars of size 4 m × 4 m are left at an interval of 13 m along the length of the stope (255 m long, 6.0 m wide). If the density of the mined ore is 2.5 tonne m-3, and slices are extracted to the full stope width, the total tonnage of ore recovered from the 1st slice (4.8 m thick) of the stope is ___________ ×103. (rounded off to one decimal place)

Correct : 14.7

Similar Questions

A trapezium has vertices marked as P, Q, R and S (in that order anticlockwise). The side PQ is parallel to side SR. Further, it is given that, PQ = 11 cm, QR...
#4 MCQ
Mosquitoes pose a threat to human health. Controlling mosquitoes using chemicals may have undesired consequences. In Florida, authorities have used geneticall...
#6 MCQ
Consider the following inequalities. (i) 2π‘₯ βˆ’ 1 > 7 (ii) 2π‘₯ βˆ’ 9 < 1 Which one of the following expressions below satisfies the above two inequalities?
#7 MCQ

Related Topics

cut and fill stope mining engineering gate ore recovery mined ore density 1st slice tonnage mining engineering 2026 stope dimensions mining engineering questions

Unique Visitor Count

Total Unique Visitors

Loading......