Mining Engineering > GATE 2026 > Systems Engineering - Queueing Theory
A shovel needs to be selected from four models of different capacities, S1 to S4, for loading of dumpers. The operational data for the shovel-dumper combination are provided. The mean arrival rate of the dumpers at the loading point is 5 per hour and the waiting cost of dumper is ₹ 200 per hour. The inter-arrival time of dumpers and loading time of shovel follows exponential distribution. Ignoring the shovel hiring cost, the shovel type that will have minimum total cost (waiting and operating cost) is
Model Operating cost (₹/hr) Mean loading rate (dumpers/hr)
S1 800 8
S2 850 9
S3 920 10
S4 1000 11
A
S1
B
S2
C
S3
D
S4

Correct : b

Similar Questions

A trapezium has vertices marked as P, Q, R and S (in that order anticlockwise). The side PQ is parallel to side SR. Further, it is given that, PQ = 11 cm, QR...
#4 MCQ
Mosquitoes pose a threat to human health. Controlling mosquitoes using chemicals may have undesired consequences. In Florida, authorities have used geneticall...
#6 MCQ
Consider the following inequalities. (i) 2π‘₯ βˆ’ 1 > 7 (ii) 2π‘₯ βˆ’ 9 < 1 Which one of the following expressions below satisfies the above two inequalities?
#7 MCQ

Related Topics

shovel-dumper combination mining engineering GATE 2026 minimum total cost exponential distribution shovel selection dumpers arrival rate loading time shovel GATE mining engineering shovel operating cost dumpers loading rate shovel selection mining GATE 2026 mining engineering dumpers arrival exponential shovel selection cost GATE mining engineering question shovel selection mining engineering GATE mining engineering 2026 shovel selection cost mining GATE mining engineering question 41

Unique Visitor Count

Total Unique Visitors

Loading......