Mining Engineering > GATE 2026 > Mine Planning - PERT/CPM
The expected time (P days) and standard deviation (Q days) of the different activities (A to F) in a project are indicated in the network diagram as (P, Q). The standard deviation of the project completion time, in days, is __________. (rounded off to one decimal place)

Correct : 3.0

Similar Questions

A trapezium has vertices marked as P, Q, R and S (in that order anticlockwise). The side PQ is parallel to side SR. Further, it is given that, PQ = 11 cm, QR...
#4 MCQ
Mosquitoes pose a threat to human health. Controlling mosquitoes using chemicals may have undesired consequences. In Florida, authorities have used geneticall...
#6 MCQ
Consider the following inequalities. (i) 2π‘₯ βˆ’ 1 > 7 (ii) 2π‘₯ βˆ’ 9 < 1 Which one of the following expressions below satisfies the above two inequalities?
#7 MCQ

Related Topics

project network diagram GATE Mining Engineering 2026 project completion time standard deviation project mining engineering gate project network diagram GATE GATE 2026 question 30 project completion time deviation

Unique Visitor Count

Total Unique Visitors

Loading......