The information of a mining project for a life of three years is given below:
Applicable tax rate =30%
Discount rate =10%
If straight line depreciation with zero salvage value is applicable, the NPV, in Crore Rupees, is ______ (rounded off to 2 decimal places)

Correct : 19.99