A continuous miner serves two shuttle cars of 12 tonne capacity each. Shuttle cars I and II operate with a total cycle time of 12 minutes and 15 minutes respectively, which includes loading time of 8 minutes for each car. The production rate of the continuous miner, in tonne/hour, is ______ (rounded off to 2 decimal places)

Correct : 75.00