Mining Engineering > GATE 2025 > Surface Mining
In a shovel dumper combination, the loading time of a dumper is 3 minutes. The shovel serves 8 dumpers. If the cycle time of a dumper including its loading time is 22 minutes, the waiting time of a dumper, in minute, is ______ (in integer)