Mining Engineering > GATE 2024 > Mine Economics
The real rate of return from a mining project is 14%. If the inflation rate over the entire life of the mine is 5.5%, then the nominal rate of return in %, is _________.(round off up to 2 decimals)
Correct : 20.07