Mining Engineering > GATE 2024 > Mine Transportation
A transportation system for carrying ore from stock pile to railway siding through an ore bin is shown. The time between failure of each conveyor belt follows an exponential distribution with mean time between failure of 700 hours. The system is considered to be a 'success' if ore transports from stock pile to siding by any combination of belts. The reliability of the system for 350 hours of continuous successful operation, is __________. (round off up to 2 decimals)


Correct : 0.74
Similar Questions
A 35.0 kW motor transmits power to a pulley of 600 mm diameter, which rotates at 400 rpm to drive a flat belt. The tension in the tight side is 2.5 times of the...
The correct order of pavement layers for a haul road from top to bottom is
In a small metal mine a battery powered locomotive hauls a train of mine tubs such that: The weight of the train of mine tubs, tonne: 3.0 The coefficient of f...