Mining Engineering > GATE 2024 > Project Management
A project network with the
The crashing costs of activities are
If the project is crashed by one week, the increase in project cost, in lakh INR, is
A
2.0
B
2.5
C
3.0
D
4.0

Correct : a

Similar Questions

In project scheduling techniques, the CORRECT statement is
#77 MCQ
Information on Activity-Time duration of a project is provided below The expected project duration in weeks, is _________. (in integer)
#179 Fill in the Blanks
A project network consists of the following activities Activity If the project completion time is 30 days, then the value of 'X', in days, is ________. [in...
#229 Fill in the Blanks

Related Topics

project network crashing mining engineering gate 2024 project crashing costs mining project cost increase GATE mining engineering 2024 activity crashing costs project network analysis cost increase project crash