Mining Engineering > GATE 2023 > Stope Design
A mine void of width 20 m, length 50 m and height 30 m is to be filled with mill tailings based cemented paste backfill (CPB). The CPB contains tailings:cement: water as 1.0:0.1:0.2 by weight. The specific gravity of tailings and cement are 2.8 and 2.4 respectively. Assuming 20% of the original volume of water is retained in the final backfill, the amount of cement in tonne required so as to fill the void completely is ________. [rounded off to nearest integer]

Correct : 3077

Similar Questions

A trapezium has vertices marked as P, Q, R and S (in that order anticlockwise). The side PQ is parallel to side SR. Further, it is given that, PQ = 11 cm, QR...
#4 MCQ
Mosquitoes pose a threat to human health. Controlling mosquitoes using chemicals may have undesired consequences. In Florida, authorities have used geneticall...
#6 MCQ
Consider the following inequalities. (i) 2π‘₯ βˆ’ 1 > 7 (ii) 2π‘₯ βˆ’ 9 < 1 Which one of the following expressions below satisfies the above two inequalities?
#7 MCQ

Related Topics

mining engineering gate 2023 void filling with CPB GATE Mining Engineering 2023 cemented paste backfill tailings cement water ratio specific gravity cement tailings void filling cement required GATE 2023 question 63

Unique Visitor Count

Total Unique Visitors

Loading......