Mining Engineering > GATE 2023 > Transportation
A coal company has three mines which transport coal to four washeries. The daily production from each mine, the demand at each washery and unit transportation cost from each mine to each washery are given in table
The cost of initial basic feasible solution using Vogel's approximation method is _______. [rounded off to 1 decimal place]

Correct : 18900.0

Similar Questions

A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution...
#231 Fill in the Blanks
A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution...
#231 Fill in the Blanks
A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution...
#231 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......