Mining Engineering > GATE 2023 > Mine Safety
As per DGMS guidelines, the risk score in Safety Management Plan for a hazard is computed as
A
Consequence × Exposure
B
Consequence × Exposure × Probability
C
Exposure × Probability
D
Consequence × Probability

Correct : b