Mining Engineering > GATE 2023 > Project Management
In project scheduling techniques, the CORRECT statement is
A
Both CPM and PERT are deterministic.
B
Both CPM and PERT are probabilistic.
C
CPM is deterministic and PERT is probabilistic.
D
CPM is probabilistic and PERT is deterministic.

Explanation

Correct : c