Mining Engineering > GATE 2023 > Project Management
In project scheduling techniques, the CORRECT statement is
A
Both CPM and PERT are deterministic.
B
Both CPM and PERT are probabilistic.
C
CPM is deterministic and PERT is probabilistic.
D
CPM is probabilistic and PERT is deterministic.

Correct : c

Similar Questions

A project network with the The crashing costs of activities are If the project is crashed by one week, the increase in project cost, in lakh INR, is
#30 MCQ
Information on Activity-Time duration of a project is provided below The expected project duration in weeks, is _________. (in integer)
#179 Fill in the Blanks
A project network consists of the following activities Activity If the project completion time is 30 days, then the value of 'X', in days, is ________. [in...
#229 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......