Mining Engineering > GATE 2022 > Mine Planning
A mine has a reserve of 150 million tonne (Mt) and is designed for a maximum production capacity of 5 Mt per year. In the first year the production is 2 Mt and it increases by 20% each year. The reserve in Mt that remains at the end of 15 years, is _________. (round off to two decimal places)

Correct : 84.80

Similar Questions

In an open pit mine, the mineral inventory, prices, costs and capacities are given. The mine is operating at 5 million tonne in a year. Considering mining...
#48 Fill in the Blanks
The grade-tonnage distribution for the ultimate pit of a mine is given below. The mill cut-off grade is 0.5% Cu. The annual mining capacity (ore + waste) is 4....
#232 Fill in the Blanks
In the context of mine planning, match the following:
#340 MCQ

Related Topics

mining engineering GATE 2022 mine reserve depletion GATE mining engineering annual production increase mining engineering production mining engineering depletion mine reserve calculation mining engineering depletion rate mine reserve depletion GATE

Unique Visitor Count

Total Unique Visitors

Loading......