Mining Engineering > GATE 2022 > Refrigeration and Air Conditioning
An underground AC plant requires the delivery of 250 US gpm (15.85 US gpm = 1.0 lps) of chilled water. For this purpose, ice-pellets at 0°C temperature (latent heat of melting, 334 kJ/kg) are mixed with water at 20°C (specific heat 4.18 kJ/kg0C) on the surface. The mixture is adiabatically transported to the underground location such that the water at 7°C becomes available for the AC plant. The requirement of ice-pellets in tonne/hr to meet the design condition, is __________. (round off to two decimal places)
Correct : 7.00
Similar Questions
A trapezium has vertices marked as P, Q, R and S (in that order anticlockwise).
The side PQ is parallel to side SR.
Further, it is given that, PQ = 11 cm, QR...
Mosquitoes pose a threat to human health. Controlling mosquitoes using
chemicals may have undesired consequences. In Florida, authorities have used
geneticall...
Consider the following inequalities.
(i) 2𝑥 − 1 > 7
(ii) 2𝑥 − 9 < 1
Which one of the following expressions below satisfies the above two
inequalities?
Total Unique Visitors
Loading......