Mining Engineering > GATE 2022 > Underground Coal Mining
The extraction ratio during development of a bord and pillar panel is 0.15 in a flat coal seam. The panel is further extracted by widening the galleries, and the extraction ratio changes to 0.25. The percentage change in pillar stress, considering tributary area method, is ____________. (round off to two decimal places)

Explanation

Correct : 13.00