Mining Engineering > GATE 2021 > Mine Planning
The grade-tonnage distribution for the ultimate pit of a mine is given below.
The mill cut-off grade is 0.5% Cu. The annual mining capacity (ore + waste) is 4.5 million tonne and milling capacity is 1.0 million tonne. Excavation is planned in such a way that either of the mine or the mill runs at full capacity throughout. The planned life of the mine, in years, is [round off to one decimal place]

Correct : 6.0

Similar Questions

In an open pit mine, the mineral inventory, prices, costs and capacities are given. The mine is operating at 5 million tonne in a year. Considering mining...
#48 Fill in the Blanks
A mine has a reserve of 150 million tonne (Mt) and is designed for a maximum production capacity of 5 Mt per year. In the first year the production is 2 Mt and...
#178 Fill in the Blanks
In the context of mine planning, match the following:
#340 MCQ