Mining Engineering > GATE 2021 > Transportation
A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution centre, and the associated transportation cost per tonne from factory to distribution centre are given in the Table.
The initial basic feasible solution using the least-cost rule is _______. [in integer]

Correct : 112000

Similar Questions

A coal company has three mines which transport coal to four washeries. The daily production from each mine, the demand at each washery and unit transportation c...
#112 Fill in the Blanks
For a mining company the unit transportation cost from a mine to a washery, and supply and demand are shown below: The total cost of transportation using th...
#356 Fill in the Blanks
The figure depicts a transportation problem along with the solution. The correct statement is