Mining Engineering > GATE 2021 > Project Management
A project network consists of the following activities Activity
If the project completion time is 30 days, then the value of 'X', in days, is ________. [in integer]

Correct : 5

Similar Questions

A project network with the The crashing costs of activities are If the project is crashed by one week, the increase in project cost, in lakh INR, is
#30 MCQ
In project scheduling techniques, the CORRECT statement is
#77 MCQ
Information on Activity-Time duration of a project is provided below The expected project duration in weeks, is _________. (in integer)
#179 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......