Mining Engineering > GATE 2021 > Project Management
A project network consists of the following activities Activity
If the project completion time is 30 days, then the value of 'X', in days, is ________. [in integer]

Correct : 5
Similar Questions
A project network with the
The crashing costs of activities are
If the project is crashed by one week, the increase in project cost, in lakh INR, is
In project scheduling techniques, the CORRECT statement is
Information on Activity-Time duration of a project is provided below
The expected project duration in weeks, is _________. (in integer)
Total Unique Visitors
Loading......