Mining Engineering > GATE 2021 > Project Management
A project network consists of the following activities Activity
If the project completion time is 30 days, then the value of 'X', in days, is ________. [in integer]

Correct : 5

Similar Questions

A project network with the The crashing costs of activities are If the project is crashed by one week, the increase in project cost, in lakh INR, is
#30 MCQ
In project scheduling techniques, the CORRECT statement is
#77 MCQ
Information on Activity-Time duration of a project is provided below The expected project duration in weeks, is _________. (in integer)
#179 Fill in the Blanks

Related Topics

project network analysis GATE Mining Engineering 2021 project completion time network diagram activity duration mining engineering gate GATE 2021 question 50 project network activities

Unique Visitor Count

Total Unique Visitors

Loading......