Mining Engineering > GATE 2021 > Underground Coal Mining
In a bord and pillar panel six shuttle cars, each of 10 tonne capacity, are deployed to transport coal produced by two continuous miners to a belt conveyor. Each shuttle car on an average carries 80% of its rated capacity and makes 7 round trips in an hour. The belt conveyor has a capacity such that the effective material cross section area is of 0.09 m2 and runs at a speed 1.1 m/s. The broken coal has a bulk density of 1.2 tonne/m3. The ratio between the production and the capacity of the belt conveyor, in percent is
A
65.46
B
71.42
C
78.56
D
82.46

Correct : c

Similar Questions

A Bord and Pillar panel is developed at a depth of 250 m in a flat coal seam. The vertical stress gradient is 0.027 MPa/m. If the strength of a square pillar is...
#43 Fill in the Blanks
For a continuous miner (CM) panel, the following data are given. Data related to CM A Table: Assume, unit weight of coal is 1.4 tonne/m3 and its swell facto...
#54 Fill in the Blanks
'Critical subsidence has occurred on the surface due to mining of a flat longwall panel at a depth of 200 m. The width of the panel is 150 m. The maximum width...
#87 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......