Mining Engineering > GATE 2020 > Mineral Processing
An underground copper mine sends 2500 tonnes of ore per day to the concentrator plant having an average grade of 1.2% Cu. The plant produces concentrate of 25.0% Cu with a recovery of 93.0%. The solids portion of tailings generated from the plant per day in tonnes is __________. (round off to 1 decimal place).
Correct : 2380.0
Similar Questions
A thermal power plant has an agreement with three mines M1, M2 and M3 to receive 'Grade 1' coal, in the proportion of 60%, 25% and 15%, respectively. The probab...
In a quality control process of coal supplied to a thermal plant, the 3-sigma control limits for fixed carbon (FC) are defined by 40%±15%. The process is...
A deposit has the grade attribute X∈ with a density function f(x). For a cut-off grade xc, the proportion of the ore in the deposit is given by