Mining Engineering > GATE 2020 > Queuing Theory
In a mine bench, the shovel loading time follows exponential distribution with a mean loading time of 5 min per dumper. The arrival rate of dumpers that are identical in capacity, follows Poisson distribution with a mean arrival rate of 8 per hour. The probability that the shovel remains idle is ________. (round off to 2 decimal places).

Correct : 0.32