Mining Engineering > GATE 2020 > Earthmoving Machinery
A shovel of bucket capacity 4.2 m3 makes 900 passes per day with a fill factor of 0.8. If the swell factor of the rock is 1.4, then in-situ volume handled by the shovel in a month of 24 working days in m3 is _________. (round off to 1 decimal place).

Correct : 51830.0