Mining Engineering > GATE 2019 > Earthmoving Machinery
A shovel operates 300 days in a year, 2 shifts in a day, and 4 hours in a shift to achieve the target production of 30 Million tonne per annum. The following parameters relate to the loading operations:
The minimum number of shovels required to achieve the production is _________.

Explanation

Correct : 4