Mining Engineering > GATE 2019 > Underground Coal Mining
A double ended ranging drum shearer operates in a longwall retreating panel. The following data are provided
Method of cutting is unidirectional and each shift requires a non-operational time of 2.0 hours. The production per day in tonne (rounded off to one decimal place) is

Correct : 2450.1