Mining Engineering > GATE 2019 > Mine Planning
In the context of mine planning, match the following:
A
P-4, Q-3, R-2, S-1
B
P-1, Q-2, R-3, S-4
C
P-1, Q-4, R-2, S-3
D
P-3, Q-2, R-4, S-1

Correct : a

Similar Questions

In an open pit mine, the mineral inventory, prices, costs and capacities are given. The mine is operating at 5 million tonne in a year. Considering mining...
#48 Fill in the Blanks
A mine has a reserve of 150 million tonne (Mt) and is designed for a maximum production capacity of 5 Mt per year. In the first year the production is 2 Mt and...
#178 Fill in the Blanks
The grade-tonnage distribution for the ultimate pit of a mine is given below. The mill cut-off grade is 0.5% Cu. The annual mining capacity (ore + waste) is 4....
#232 Fill in the Blanks

Related Topics