Mining Engineering > GATE 2019 > Winding
The correct sequence of attachments between the winding rope and the cage in a drum winding system is
A
Triangular plate → Rope capel→ Bull chain → Detaching hook → Cage chain
B
Rope capel→ Bull chain → Triangular plate → Detaching hook → Cage chain
C
Detaching hook → Rope capel→ Bull chain Cage chain → Triangular plate
D
Rope capel→ Detaching hook → Bull chain → Triangular plate → Cage chain

Correct : d

Similar Questions

In a friction winder, the skip accelerates to a steady speed over a time span of 15 s from the start. The torque vs. time diagram for the winding cycle is shown...
#148 Fill in the Blanks
Ore is hoisted from 620 m depth using a single skip of 7 tonne pay load. The skip winding system has constant acceleration/deceleration of 1 m/s2 and a constant...
#222 Fill in the Blanks
Match the following safety arrangements for a surface-to-underground shaft hoist with their corresponding safety functions.
#247 MCQ

Related Topics

drum winding system winding rope cage attachment GATE Mining Engineering 2019 mining engineering gate correct sequence attachments mining engineering gate questions rope capel bull chain winding system attachments

Unique Visitor Count

Total Unique Visitors

Loading......