Mining Engineering > GATE 2019 > Project Management
In project planning, the activity durations are calculated by PERT and CPM techniques assuming
A
PERT: probabilistic, CPM: deterministic
B
PERT: probabilistic, CPM: probabilistic
C
PERT: deterministic, CPM: probabilistic
D
PERT: deterministic, CPM: deterministic

Correct : a