Mining Engineering > GATE 2019 > Blasting
The PV diagram of four explosives is given below. The preferred explosive for adequate fragmentation in hard and brittle rock is
A
Explosive A
B
Explosive B
C
Explosive C
D
Explosive D

Correct : a

Similar Questions

In an opencast coal mine, blast vibrations are measured at two locations, A and B simultaneously for a maximum charge per delay (Q) of 1200 kg as given. Ass...
#51 Fill in the Blanks
In a development coal face, 12 holes are drilled and charged with explosive. Holes are initiated with electric delay detonators connected in series. The length...
#55 Fill in the Blanks
The blast pattern of a coal face shown in the figure Front view Top view Side view represents _______.
#67 MCQ

Related Topics