Mining Engineering > GATE 2018 > Blasting
The following figure shows the designed blast pattern of a bench. The explosive column is charged at 18 kg/m. If the unit weight of the blasted material is 2.5 tonne/m3, the powder factor for the blast in tonne/kg is _____________.

Explanation

Correct : 2.00