Mining Engineering > GATE 2018 > Surface Mining
In a level terrain, a vertical orebody of 20 m uniform width is worked by surface mining method. The density of the ore is 2.5 tonne/m3. The ultimate pit has a depth of 60 m, width of 20 m at pit bottom, and a pit slope of 45° The overall stripping ratio for this condition in m3/tonne is _____________.

Correct : 1.2

Similar Questions

In a shovel dumper combination, the loading time of a dumper is 3 minutes. The shovel serves 8 dumpers. If the cycle time of a dumper including its loading time...
#521 NAT
In a shovel dumper combination, the loading time of a dumper is 3 minutes. The shovel serves 8 dumpers. If the cycle time of a dumper including its loading time...
#521 NAT
In a shovel dumper combination, the loading time of a dumper is 3 minutes. The shovel serves 8 dumpers. If the cycle time of a dumper including its loading time...
#521 NAT

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......