Mining Engineering > GATE 2018 > Underground Coal Mining
Following information about a longwall retreating panel is given.
Panel length =1800 m
Face length =150 m
Depth of web=0.6 m
Shearer travels at a speed of 1.5 m/min along the face. Each cutting cycle requires a non-operational time of 2 h 20 min. The panel is fully extractable. The number of working days required to extract the panel is ________.

Correct : 500.0

Similar Questions

A Bord and Pillar panel is developed at a depth of 250 m in a flat coal seam. The vertical stress gradient is 0.027 MPa/m. If the strength of a square pillar is...
#43 Fill in the Blanks
For a continuous miner (CM) panel, the following data are given. Data related to CM A Table: Assume, unit weight of coal is 1.4 tonne/m3 and its swell facto...
#54 Fill in the Blanks
'Critical subsidence has occurred on the surface due to mining of a flat longwall panel at a depth of 200 m. The width of the panel is 150 m. The maximum width...
#87 Fill in the Blanks

Related Topics

GATE Mining Engineering 2018 longwall retreating panel shearer cutting cycle GATE 2018 Mining Q51 underground coal mining panel extraction time longwall shearer speed

Unique Visitor Count

Total Unique Visitors

Loading......