Mining Engineering > GATE 2018 > Mine Planning
Economic feasibility of two methods is examined for meeting a targeted mine production. On a yearly basis, the following cost parameters (Rs in crores) are applicable for these methods.
The annual rate of production, 'X' in million tonnes for which both the methods will yield the same operating cost is _________.

Correct : 5.0