Mining Engineering > GATE 2018 > Mine Planning
Economic feasibility of two methods is examined for meeting a targeted mine production. On a yearly basis, the following cost parameters (Rs in crores) are applicable for these methods.
The annual rate of production, 'X' in million tonnes for which both the methods will yield the same operating cost is _________.

Correct : 5.0

Similar Questions

In an open pit mine, the mineral inventory, prices, costs and capacities are given. The mine is operating at 5 million tonne in a year. Considering mining...
#48 Fill in the Blanks
A mine has a reserve of 150 million tonne (Mt) and is designed for a maximum production capacity of 5 Mt per year. In the first year the production is 2 Mt and...
#178 Fill in the Blanks
The grade-tonnage distribution for the ultimate pit of a mine is given below. The mill cut-off grade is 0.5% Cu. The annual mining capacity (ore + waste) is 4....
#232 Fill in the Blanks

Related Topics

mining engineering gate 2018 mining production cost analysis economic feasibility mining GATE mining engineering 2018 production cost methods comparison mining engineering cost parameters mining production cost GATE 2018 question 45

Unique Visitor Count

Total Unique Visitors

Loading......