Mining Engineering > GATE 2018 > Mine Ventilation
A panel in coal mine produces 400 tonne per day. The number of persons employed in each of the three shifts is 110, 130 and 120. As per CMR, the minimum quantity of air that needs to be circulated at the last ventilation connection of the panel in m3/min is
A
780
B
900
C
1000
D
2400

Correct : c

Similar Questions

A rectangular mine airway of 2.0 m width and 2.5 m height has a bend with deflection of π/4 radian. If the radius of curvature of the bend is 4.0 m, the shoc...
#24 MCQ
A rectangular face of 2.0 m×2.5 m dimension is blasted with 20 kg explosive in a 1000 m long drive. One kilogram of explosive produces 2200 cm3 of nitrous...
#40 Fill in the Blanks
To increase the resistance of a mine roadway by 1.5 Ns2m-8, the size in m2 of the regulator to be installed is _________.[rounded off to 2 decimal places]