Mining Engineering > GATE 2018 > Transportation
The figure depicts a transportation problem along with the solution. The correct statement is
A
unbalanced problem, optimal solution
B
unbalanced problem, sub-optimal solution
C
balanced problem, optimal solution
D
balanced problem, sub-optimal solution

Correct : d