Mining Engineering > GATE 2017 > Underground Coal Mining
A mine is being developed by bord and pillar method with a gallery size of 4.8 m×2.4 m. The mine operates in 3 shifts per day and 6 faces are blasted per shift. The average pull per round of blast is 1.2 m and the bulk density of coal is 1.4 t/m3. If the OMS is 2.5, then the average manpower deployed in the development section per shift is ____________.

Correct : 46 to 47

Similar Questions

A Bord and Pillar panel is developed at a depth of 250 m in a flat coal seam. The vertical stress gradient is 0.027 MPa/m. If the strength of a square pillar is...
#43 Fill in the Blanks
For a continuous miner (CM) panel, the following data are given. Data related to CM A Table: Assume, unit weight of coal is 1.4 tonne/m3 and its swell facto...
#54 Fill in the Blanks
'Critical subsidence has occurred on the surface due to mining of a flat longwall panel at a depth of 200 m. The width of the panel is 150 m. The maximum width...
#87 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......