Mining Engineering > GATE 2017 > Mine Planning
The block grade model of an ore deposit is shown in the figure below. The relationship between block value per tonne (Bv) in rupees and the block grade in percentage (x) is given below:
If each square block contains 1000 tonne of material and the overall pit slope angle is 45°, the total value of the pit determined by the floating cone algorithm in Lakhs of rupees is _________.

Correct : 25 to 27
Similar Questions
In an open pit mine, the mineral inventory, prices, costs and capacities are given.
The mine is operating at 5 million tonne in a year. Considering mining...
In an open pit mine, the mineral inventory, prices, costs and capacities are given.
The mine is operating at 5 million tonne in a year. Considering mining...
In an open pit mine, the mineral inventory, prices, costs and capacities are given.
The mine is operating at 5 million tonne in a year. Considering mining...
Total Unique Visitors
Loading......