In a PERT network, the "time estimates" of an activity are the following: Optimistic time - 2 days, Most likely time - 4 days, and Pessimistic time - 12 days. The expected time and standard deviation of the activity in days are respectively
A
6.0 and 2.78
B
5.0 and 1.66
C
6.0 and 1.66
D
5.0 and 2.78

Correct : b

Similar Questions

A project network with the The crashing costs of activities are If the project is crashed by one week, the increase in project cost, in lakh INR, is
#30 MCQ
In project scheduling techniques, the CORRECT statement is
#77 MCQ
Information on Activity-Time duration of a project is provided below The expected project duration in weeks, is _________. (in integer)
#179 Fill in the Blanks

Related Topics

PERT network expected time PERT standard deviation GATE Mining Engineering 2017 GATE Mining 2017 Q15 optimistic time pessimistic time project management PERT expected time standard deviation PERT

Unique Visitor Count

Total Unique Visitors

Loading......