Mining Engineering > GATE 2017 > Project Management
In a PERT network, the "time estimates" of an activity are the following: Optimistic time - 2 days, Most likely time - 4 days, and Pessimistic time - 12 days. The expected time and standard deviation of the activity in days are respectively
A
6.0 and 2.78
B
5.0 and 1.66
C
6.0 and 1.66
D
5.0 and 2.78

Correct : b

Similar Questions

A project network with the The crashing costs of activities are If the project is crashed by one week, the increase in project cost, in lakh INR, is
#30 MCQ
In project scheduling techniques, the CORRECT statement is
#77 MCQ
Information on Activity-Time duration of a project is provided below The expected project duration in weeks, is _________. (in integer)
#179 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......