Metallurgical Engineering > GATE 2020 > Casting
In a top gated mold, liquid metal enters the mold cavity as a freely falling stream under gravity from a height of 0.5 m. Ignore the fluid friction due to viscosity and the drag due to changes in the direction of flow. If the volume of the mold cavity is 10 m³ then the time required to fill the mold is _______ s (round off to nearest integer).
Given:
1. Acceleration due to gravity is 9.8 m⋅s⁻².
2. Cross-sectional area of gate is 0.2 m².

Correct : 16

Similar Questions

In casting, for a simple vertical gating system with a gate of cross-sectional area 2 cm2 and spruce height of 10 cm, the filling time for a mould of dimensions...
#72 Fill in the Blanks
Compared to top gating, the effect(s) of bottom gating in sand mold casting is/are _______.
#125 MSQ
In green sand moulding, the casting defect resulting from the displacement of mould cavity by an oversized core is known as _______.
#157 MCQ

Related Topics