Metallurgical Engineering > GATE 2019 > Steelmaking
The correct sequence of steelmaking operations is _______
[BOF: Basic Oxygen Furnace; LF: Ladle Furnace; VD: Vacuum Degassing; CC: Continuous Casting].
A
BOF → LF → VD → CC
B
CC → BOF → LF → VD
C
VD → CC → BOF → LF
D
LF → BOF → VD → CC

Correct : a