Metallurgical Engineering > GATE 2018 > Fundamentals of Iron and Steel Making
Arrange the following in the correct sequence of operations in an integrated steel plant:
i. Basic Oxygen Furnace (BOF)
ii. Blast Furnace (BF)
iii. Ruhrstahl Heraeus Degassing Process (RH)
iv. Ladle Furnace Process (LF)
A
BOF→BF→LF→RH
B
BF→LF→BOF→RH
C
RH→LF→BF→BOF
D
BF→BOF→LF→RH

Correct : d