Mechanical Engineering > GATE 2026 > PERT-CPM
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic (to), most likely (tm), and pessimistic (tp) are given in the table below.
Activity Time (in weeks)
to tm tp
1−2 2 4 12
1−3 2 4 6
1−4 3 4 11
2−5 3 6 9
3−4 2 5 14
3−5 3 3 3
4−5 3 6 15
5−6 2 5 8
The expected project length is ________ weeks (in integer).

Correct : 19