Mechanical Engineering > GATE 2026 > Production Planning
Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
Which job(s) has/have critical ratio less than unity?
A
Job N and Job O
B
Job M and Job N
C
Job P
D
Job O and Job P

Correct : b