A plate of 30 mm thickness is fed through a rolling mill with two powered rolls. Each roll has a diameter of 500 mm. The plate thickness is to be reduced to 27 mm in a single pass. Assume no change in width. The process feasibility and the maximum draft (in mm) can be represented, respectively, as
Use the coefficient of friction as 0.12
A
feasible and 3.6
B
NOT feasible and 2.6
C
feasible and 3.0
D
NOT feasible and 6.0

Correct : a

Similar Questions

The size distribution of the powder particles used in Powder Metallurgy process can be determined by
#46 MCQ
The "Earing" phenomenon in metal forming is associated with
#186 MCQ
A 4 mm thick aluminum sheet of width w = 100 mm is rolled in a two-roll mill of roll diameter 200 mm each. The workpiece is lubricated with a mineral oil, wh...
#316 Fill in the Blanks

Related Topics

plate rolling process mechanical engineering gate 2025 roll reduction thickness coefficient friction draft calculation plate rolling GATE ME 2025 question 41 feasible roll reduction maximum draft plate rolling plate thickness reduction

Unique Visitor Count

Total Unique Visitors

Loading......