Mechanical Engineering > GATE 2025 > Metal Forming
A plate of 30 mm thickness is fed through a rolling mill with two powered rolls. Each roll has a diameter of 500 mm. The plate thickness is to be reduced to 27 mm in a single pass. Assume no change in width. The process feasibility and the maximum draft (in mm) can be represented, respectively, as
Use the coefficient of friction as 0.12
A
feasible and 3.6
B
NOT feasible and 2.6
C
feasible and 3.0
D
NOT feasible and 6.0

Correct : a